Phase 1 Architectural Design
Previous slide
Next slide

Work Plan for 2022

Project is divided into multiple phases of construction. Each phase will be started and completed as enough funds become available. As Master Ishwar Ji always said, the money will come exactly when it is needed. For 2022 ISHA has budgeted $800,000 for Phase 1 (design and initial construction). 

Here are the principal Phase 1 Design tasks for Spring 2022:

  • Architects visit site, survey property, and meet with local officials
  • Complete development of Meeting Hall design
  • Submit building plan for preliminary local approvals
  • Submit “Notice of Intent” to Wisconsin Dept. of Natural Resources
  • Complete construction documents
  • Submit plans for state review
  • Complete sub-contractor bidding
  • Receive early permit to begin pouring concrete foundations
  • Receive final state building plan approval
Phase 1 Architectural Design
Previous slide
Next slide

Work Plan for 2022

Project is divided into multiple phases of construction. Each phase will be started and completed as enough funds become available. As Master Ishwar Ji always said, the money will come exactly when it is needed. For 2022 ISHA has budgeted $800,000 for Phase 1 (design and initial construction). 

Here are the principal Phase 1 Design tasks for Spring 2022:

  • Architects visit site, survey property, and meet with local officials
  • Complete development of Meeting Hall design
  • Submit building plan for preliminary local approvals
  • Submit “Notice of Intent” to Wisconsin Dept. of Natural Resources
  • Complete construction documents
  • Submit plans for state review
  • Complete sub-contractor bidding
  • Receive early permit to begin pouring concrete foundations
  • Receive final state building plan approval
Phase 1 Architectural Design
Previous slide
Next slide
Work Plan for 2022

Project is divided into multiple phases of construction. Each phase will be started and completed as enough funds become available. As Master Ishwar Ji always said, the money will come exactly when it is needed. For 2022 ISHA has budgeted $800,000 for Phase 1 (design and initial construction). 

Here are the principal Phase 1 Design tasks for Spring 2022:

  • Architects visit site, survey property, and meet with local officials
  • Complete development of Meeting Hall design
  • Submit building plan for preliminary local approvals
  • Submit “Notice of Intent” to Wisconsin Dept. of Natural Resources
  • Complete construction documents
  • Submit plans for state review
  • Complete sub-contractor bidding
  • Receive early permit to begin pouring concrete foundations
  • Receive final state building plan approval